0.7.2 Planning
Posted: Thu Aug 02, 2012 5:29 pm
Just a rough draft of some things I'd like to see accomplished in the 0.7.2 cycle. I'd like to keep it relatively small, since we're months behind where I thought we'd be due to the loss of, well, pretty much everyone's interest except Jabantiz
Tasks on Projman (link)
Things to finish off (by priority):
1.I'd like to finish the Alternate Advancement - at least the UI support, not necessarily all the spells and scripts. DONE!
2.Finish Rules System - This is going to be critical moving forward because I'm going to need Zone Rules, vs World/Global Rules. Ongoing, Delayed
Finish Log System - Scatman needs to add "queuing" so the messages stop overwriting themselves when we turn on a lot of debug logging. DONE!
New Stuff (by priority):
1. Tradeskills - 100% if possible In Progress
2.Pets - At least summoning and they follow you around DONE!
3. Instancing - A system is already started,but Scatman wanted to start over - figure this is needed for Tradeskill instances (though not critical) In Progress
Misc (no priority):
- Zone stuff -
As with all lists that I make, this is just my opinion. Discussion is welcome if you think there should be something else in the next release, or if you think I've left out finishing something else important.
I will be updating ProjMan a lot over the coming weeks to try and schedule us out through 0.7.5, which at the current rate might be 2 more years
but we'll see.
Edit: (2013.04.11) We've finished most of the stuff on this list, aside from a few things that require additional planning first. Going go finish up 0.7.2 by April 30, 2013 and start the next cycle.
Tasks on Projman (link)
Things to finish off (by priority):
1.
2.
- * Finish Zone Rules
* Add ability to change rules/rulesets from inside the game on-the-fly Ongoing, Delayed
New Stuff (by priority):
1. Tradeskills - 100% if possible In Progress
2.
3. Instancing - A system is already started,
Misc (no priority):
- Zone stuff -
- *
JA's continued work on conditional spawnsDelayed
*discovery locationsDelayed
*Weather systemDONE!
As with all lists that I make, this is just my opinion. Discussion is welcome if you think there should be something else in the next release, or if you think I've left out finishing something else important.
I will be updating ProjMan a lot over the coming weeks to try and schedule us out through 0.7.5, which at the current rate might be 2 more years
Edit: (2013.04.11) We've finished most of the stuff on this list, aside from a few things that require additional planning first. Going go finish up 0.7.2 by April 30, 2013 and start the next cycle.